A design and build contract in Kenya is the document that decides who pays when something goes wrong on your building site. With design and build, one firm takes responsibility for the drawings, the approvals and the construction of your house, which removes the blame game between architect and builder that stalls so many Kenyan projects. If you are new to the method, start with our main guide, Design and Build in Kenya: why one contractor from plan to handover saves you time and money.
That single point of responsibility only protects you if the contract is written properly. Many homeowners sign a two-page letter that names a total price and a deposit, and nothing else. This guide explains, clause by clause, what a sound design and build contract should contain, what a fair payment schedule looks like, and the questions to ask before you sign.
Planning to build? Get a free building quote and a draft scope for your house from our team: WhatsApp 0789 217 685
What is a design and build contract in Kenya?
Under a traditional arrangement you hire an architect, a quantity surveyor and engineers, they produce drawings and a Bill of Quantities (BQ), and contractors then bid to build. Under a design and build contract, one firm is appointed to do both: it develops the design from your brief, prepares the BQ, obtains approvals and builds. The contract therefore has to cover two jobs at once — a design service and a construction service — and it must say clearly where your responsibility ends and the contractor’s begins. If you are still weighing the two methods, see this comparison of design and build vs traditional construction in Kenya and the explainer What is design and build?

12 clauses every design and build contract should include
1. The parties and their registration
Full names, ID or company registration numbers, physical addresses and the contractor’s National Construction Authority registration category. The National Construction Authority was established under the NCA Act No. 41 of 2011 to oversee the construction industry, so ask for the certificate and check that the category suits the size of your project. Because the firm is also your designer, the contract should name the registered architect or engineer responsible for the drawings; architects and quantity surveyors are regulated by the Board of Registration of Architects and Quantity Surveyors.
2. Your brief and the scope of work
Attach your brief: number of bedrooms, approximate floor area, roof type, finishes level and anything you consider essential (a DSQ, a water tank stand, a perimeter wall). State exactly what is included and what is excluded. Fencing, gates, landscaping, borehole, septic tank or soak pit, KPLC connection, water connection and built-in furniture are the items most often left out and later billed as extras.
3. Design deliverables and approvals
List the drawings you will receive (architectural, structural, plumbing and electrical), the BQ, and who submits and pays for county approval and any NEMA requirements. Say how many rounds of design changes are included before the design is frozen, and that you own a copy of the approved drawings at the end.
4. The contract sum and what it is based on
The price should be tied to the approved drawings and a priced BQ, not to a verbal estimate. State whether it is a fixed lump sum or subject to remeasurement, how provisional sums (for items not yet designed) are handled, and whether VAT is included.
5. A payment schedule tied to milestones
Pay for work done, not for time passed. Each instalment should be linked to a stage you can see and inspect (see the illustration below). For more on structuring payments, read payment schedules in construction projects.
6. Retention
A small percentage held back from each payment, or from the final payment, and released only after the defects period. It gives the contractor a reason to come back and fix problems.
7. Variations
Changes will happen. The contract should say that no variation is carried out without a written instruction showing the cost and time effect, signed by you before the work starts. This one clause prevents most budget disputes.
8. Programme, completion date and delays
Attach a stage-by-stage programme. Say what happens if the contractor is late without good reason, and also what counts as an acceptable delay (heavy rain, late payment by you, approval delays).
9. Materials, specifications and quality checks
Name the key materials: walling stone or blocks, cement class, steel sizes, roofing sheet gauge or tile type, window and door specification, sanitary ware and tile grade. Include inspections at foundation, before each concrete pour and before roofing, plus concrete cube tests for slabs and beams.
10. Insurance and site safety
Who insures the works, workers and neighbours’ property during construction, and who is responsible for site security and materials kept on site.
11. Defects liability period
A fixed period after handover during which the contractor must return and repair defects such as cracks, leaks and faulty fittings at its own cost. Agree the length in writing and link the release of retention to it.
12. Handover documents, disputes and termination
At handover you should receive as-built drawings, warranties for roofing, pumps and fittings, keys, and support with the occupation certificate. The contract should also explain how disputes are settled (meeting, then mediation, then arbitration or court) and how either side can end the contract fairly.
What a fair milestone payment schedule looks like
To give a sense of scale, here are indicative build costs using the Integrum construction cost rates (updated October 2026; indicative planning figures, not quotations):
| House type | Floor area | Western & Nyanza (KSh) | Nairobi (KSh) |
|---|---|---|---|
| Standard 3-bedroom bungalow | 120 m² | 6,849,600 (57,080/m²) | 6,567,600 (54,730/m²) |
| Middle-class 4-bedroom maisonette | 200 m² | 13,848,000 (69,240/m²) | 12,214,000 (61,070/m²) |
The table below is an illustration only, not a standard: it shows how a KSh 6,849,600 contract for the bungalow above could be split so that every payment follows visible progress. Your own schedule should follow your BQ and programme.
| Milestone (inspected before payment) | Share | Amount (KSh) |
|---|---|---|
| Signed contract, approved drawings, site set-out | 10% | 684,960 |
| Foundation and ground floor slab complete | 20% | 1,369,920 |
| Walling up to ring beam complete | 20% | 1,369,920 |
| Roof structure and covering complete | 15% | 1,027,440 |
| Plastering, plumbing and electrical first fix | 15% | 1,027,440 |
| Finishes complete and handover | 15% | 1,027,440 |
| Retention, released after the defects period | 5% | 342,480 |
| Total | 100% | 6,849,600 |
If you plan to fund the house in stages, agree pauses in the programme from the start; our guide on building a house in phases in Kenya explains how to do it without stalling.
Common mistakes homeowners make with building contracts
- Paying a large deposit before drawings are approved or any work is on site.
- Accepting a price per square metre without a BQ, so nobody can show what is included.
- Agreeing changes on the phone and arguing about the cost later.
- No named materials, so cheaper substitutes are used without your knowledge.
- No retention and no defects period, so cracks and leaks after handover become your cost.
- Leaving external works (septic tank, water and power connections, fence) out of the scope and discovering the gap at the end.
- Signing without an advocate reading the document. This guide is practical advice, not legal advice; have a lawyer review your contract.

Questions to ask before you sign
- Can I see your NCA certificate and the registration of the architect or engineer who will sign the drawings?
- Is your price based on a priced BQ, and can I have a copy?
- What exactly is excluded from the contract sum?
- How many design revisions are included, and when is the design frozen?
- Who applies and pays for county approval and NEMA requirements?
- What is each payment linked to, and how do I inspect before paying?
- How are variations priced and approved?
- How will you report progress — photos, videos, site visits? (Essential if you are choosing a contractor from abroad.)
- How long is the defects period and how much retention is held?
- Can I visit or speak to the owner of a house you have completed?
How West Kenya Real Estate structures its design and build contracts
West Kenya Real Estate Ltd is an NCA-registered Design and Build firm with offices in Kisumu and Nairobi. We start from your brief and budget, produce the drawings and a BQ, and only then agree a contract sum, with payments linked to stages you can inspect. If you already like a ready design, such as this modern 3-bedroom bungalow plan with DSQ or the simple 4-bedroom maisonette plan WKRE067, we can price and build it under one contract.
Looking for a contractor you can trust?
Send us your plot location, the house you have in mind and your budget on WhatsApp. We will reply with a free indicative quote and explain what our design and build contract covers, stage by stage.
Or call 0789 217 685 / 0724 481 087.